June 2023

Excavation for houses and placement of earth screws
July 2023

It even gets a parking lot of skeleton parts for all the houses
End of July, beginning of August 2023

From the end of July to the beginning of August 2023, skeletons grow
August 2023

“Dressing” the skeleton, painting the platforms, preparing the roof
August, September 2023
Roofing, concreting

October 2023

Preparation of the walls for the facade, treatment of the walls for the windows, finally – the houses are closed before winter
November, December 2023 and January 2024
Facade and interior design of houses

February 2024

Digging trenches for water and electricity, making interior work in houses
March and April 2024

Landscaping and work inside the houses
Spring 2024

During the implementation of the project, there is a lot of other work, the most important, of course, is taking care of the bees
June 2024

Painting the side crosses and patio timbers and formwork and putting everything in place
June 2024

In July, the sun brightens, the external image of Apithurism Kr’Bee takes its final form